ACE

Cost Estimating

Making learning and teaching more effective.

A great place to be.

Service-Cost-Estimates.png

Cost Estimating

Typical Estimate Definition:

“A cost estimate may be defined as a prediction or an evaluation of all costs of the various different elements of a project or effort as defined by an agreed upon scope and execution plan.”

Purpose:

Quantify and predict the cost required to complete a project / facility.

  • Based on a defined scope of the project
  • Within an agreed timeframe

Uses:

  • Economic Viability
  • Licensor Selection
  • Feasibility Study
  • Alternatives Analysis/Optimization
  • Project Funding
  • Establish a Baseline (Project Budget)
  • Assess Change Impacts/Change Management Support
  • Bid Proposal (New Work)
  • Benchmark / Validation / Check for RFP Bids

Types of Estimates:

  • ROM Estimates
  • Engineering Screening Level Estimates – Multiple Options
  • End of Study Phase / FEED Phase Estimates
  • Detailed Estimate (Baseline/Control Base)
  • A typical cost estimate for a project includes the following major cost categories:
    • Direct Field Costs (DFC)
    • Indirect Field Costs (IFC)
    • Home Office Costs (HOC)
    • Other Costs (OC)
    • Contingency and Escalation

Estimate Execution Plan (EEP):

  • Development of Estimate Plan is responsibility of the Lead Estimator
  • Issued early following estimate kick-off meeting.
  • The Plan is the vehicle to document and obtain agreement between project team, Client and estimating team on the estimate development effort:
  • Estimate Plan defines the type / Class of estimate to be developed.
  • Estimating methodology to be utilized for the development of estimate.
  • Define the estimate input required and party responsible for the inputs.
  • Includes an estimate development schedule.
  • Defining due dates for the required input
  • Documentation to be submitted to the estimating team,
  • Estimate completion and review dates, etc.
    • Identifies major items, cost categories and overlays and defines how they are to be priced and/or estimated.

Basis of Estimate (BOE):

  • BOE describes scope of estimate / how the estimate was developed.
  • Records agreements defining how estimate was developed, the scope and major estimate assumptions.
  • The BOE Includes:
  • The estimating methodology
  • Estimate organization (WBS)
  • Brief summary of scope of facilities and schedule.
  • Listing of applicable engineering documents used.
  • Definition how major elements were priced and/or estimated.
  • Definition of any cost overlays or allowances, etc.
  • List of applicable qualifications and assumptions
  • List of estimate exclusions
  • Other applicable major items having impact on the estimate.
Scroll to Top